Project Description:

Refurbishment of the Heller UK headquarters based in Redditch. The scheme consisted of a full strip back of all services and installation of a more energy efficient scheme.

The installations included:

Mechanical

  • Full design
  • VRF System
  • Ventilation System
  • Hot & Cold Water System
  • BMS System
  • Sanitaryware
Electrical

  • Full Design
  • Distribution System
  • General Electrical Installation
  • General & Emergency Lighting
  • Fire Alarm System
  • Data & Communication
  • AV Systems

Project Duration: 20 Weeks